By NEIL HARTNELL
Tribune Business Editor
nhartnell@tribunemedia.net
The five remaining Bahamas Electricity Corporation (BEC) bidders all made additional submissions prior to Friday’s deadline, and all now await a likely presentation before a Cabinet committee.
Tribune Business was yesterday told that each group would be invited to present to the Cabinet committee overseeing the BEC/energy reform process by mid-February, with a decision on the preferred bidder/bidders likely taken by month’s end.
Simon Townend, the KPMG (Bahamas) partner and head of the company’s corporate finance arm in the Caribbean, declined to comment when contacted by Tribune Business yesterday.
However, it is understood that KPMG and the Government’s other advisers, DNV Kema and the Hogan Lovells law firm, are now assessing and sifting through the latest documents supplied by the five remaining contenders.
“They got submissions from the various bidders, and are going through them now,” a source close to the process told Tribune Business.
“The evaluation is going on, and they’ll be inviting the bidders to come and present to a committee of then Government, the Cabinet.
“The final recommendations will then go into the Government, and a decision will be made from there.”
Tribune Business understands that the plan is for all five groups to make a presentation to the Government. All have gone through the initial business plan and pricing rounds, which first saw an initial 13-strong field whittled down to nine, then five.
One of the six bidders who entered the so-called ‘pricing round’ dropped out before the November 15, 2013, bid submission deadline.
That bidder is thought to be US-based Pike Electric Company and its all-Bahamian partner, the Northern Bahamas Utilities group, comprised largely of former Grand Bahama Power Company engineers.
Tribune Business sources previously suggested Pike and its Bahamian partner dropped out around the November 15, 2013, deadline for pricing bids to be submitted.
That is understood to have left Carolinas-based Power Secure as the only bidder still in the running for the contract to manage BEC’s transmission and distribution business.
Sources close to Power Secure have expressed confidence that it is “the last man standing”, but such a development is unlikely to be welcomed by the Government and its advisers.
While there appear to be no such problems on the generation side, given that the four bidders who entered the pricing round are still surviving, the Government will have also desired competition for the transmission/distribution contract.
The fact just one bidder is left may rob the Government of the negotiating leverage a competitive bid situation would foster, and it also has nothing to compare Power Secure’s offer to.
And the new end-January deadline indicates that the BEC restructuring process, which could see the Corporation split into two, is now running between one to two months behind the original schedule.
The original August 13, 2013, tender document, a copy of which has been obtained by Tribune Business, says the Government was supposed to select the winning bidder(s) for the generation, and transmission and distribution, contracts by 2013 year-end.
It says January-February 2014 is when the Government, and winning generation and transmission and distribution bidders, are supposed to execute their respective contracts.
All the necessary permits and approvals from the relevant government agencies are supposed to be in hand by March 2014, with legislative and regulatory reform of the Bahamian energy sector accomplished the same month.
The ‘front end’ transition to the new bidders will start in April 2014, with the winning bidder(s) agreeing to be “bound by the terms of their proposals”.
The full take over of BEC’s ‘split’ operations, as per the original timetable, is supposed to happen in May.
But, given the new end-January deadline the bidders have to meet, it appears unlikely that the winner(s) will not be selected until February at the earliest.
With contract negotiations then to follow, it appears the May ‘hand over’ date is now too optimistic, with any transition likely to now take place in summer 2014. The Government’s main concern, though, will be to get the decision right.
On the generation side, one bidder is the Caribbean Power Partners consortium, headed by Texas-based Taylor Cheek and featuring Fluor Corporation and ProEnergy Services. Other bidders are thought to have originated from the Caribbean, plus China and Asia.
As revealed previously by Tribune Business, the tender documents show JVCo, or the part-privatised generation business, will be required to enter into a 20-25 year Power Purchase Agreement to sell electricity to the transmission and distribution (NewCo) entity it has just split from.
Yet the winning bidder for NewCo will, according to the tender, be given a much shorter management contract of 10 years. And, while it will have seats on NewCo’s Board, the Government is “retaining a majority of seats”.
This is despite the winning bidder having to “provide the financing/capital for performance improvement (both infrastructure and operational in nature”, and cover any costs associated with reorganising NewCo.
The transmission and distribution partner will also have to refinance the legacy BEC debt attached to NewCo without the support of any government guarantee.
When it came to the winning NewCo bidder’s management contract compensation, the tender document said “incentive payments and the sharing of cost savings” are among the options.